Difference Between Calendar Days And Work Days

 
     
  By Mukul Gupta
 
  keywords: Calendar Days Work Days Management Outsourcing.  
     
  Don’t people already know this? Well seems like “Not everybody!”

Both seasoned IT entrepreneurs as well as developers make this common mistake. They don’t seem to quite understand the difference between calendar days and work days. So let me ask you this question – “What should be the delivery date of a project starting on October 1st and having an estimated effort of 160 hours?”

A typical calculation goes like this:

160 hrs / 8 hrs per day = 20 days. So, if the project is starting on October 1st, it should all be done on 21st October. Right? Wrong!

Here is what is involved, in understanding the delivery date based on start date and total number of hours that is required to accomplish the task:

Number of Days per Week: This is the number of days for which the office of the developer’s organization is going to be open in a week. It can be any number from 5 – 6. Like some companies are open for half time on Saturday. So, this figure is 5.5 for such an organization.

Number of Hours per Day: This signifies, the number of normal work hours that developer will be working in particular day. Do not take overtime in account because then you will not have any buffer to use should the project slip.

So, based on the above two numbers, if the Number of Days per week is 5 and the number of hours per day is 8 then the developer is going to work 8 hours per day then you will 8 X 5 = 40 hours of work done per week.

This means it will take 4 weeks to get 160 hours of work done. This is an equivalent of 28 calendar days which means that given a project started on 1st October it cannot be completed before 28th October.

Granted, that the above calculation is very simple, but you get the message! In reality, things are more complex because the utilization of hours depends on other factors like Number of resources on the project, Number of parallel tasks, Holidays etc.

Why knowing this is important?

Knowing this is very important for two very important reasons:

1. It forces you to plan in advance. As you try to think about delivery dates, you automatically begin thinking about the things that affect it.

2. It prevents unnecessary dissatisfaction. Had you not known this, the delivery on October 28th would haven perceived as a 25% slippage in project deadline whereas the developer has been able to meet the deadline.

 
  keywords: Calendar Days Work Days Management Outsourcing.  
  Article Source: http://interpret.zar.vg   
     
  About The Author
Mukul Gupta is the CMO of Indus Net Technologies, an India based Internet Consulting firm which specializes in Opensource solutions. You can reach him at script@script2please.com or visit www.script2please.com
 
     
 
More Articles about: Project-Management
 
 
 
  • Difference Between Calendar Days And Work Days
  • You Want To Market Your Business, But Do You Have The Time?
  • Website Statistics for Site Analysis
  • Following The Six Sigma Operational Excellence Code
  • How To Assess The Success Of Six Sigma Implementation
  • Why Six Sigma Training Is Important
  • The IDOV Variant In Six Sigma
  • The Impact Of Six Sigma Training Certifications On Quality
  • Six Sigma And Business Continuity
  • Six Sigma Culture And Personality
  • Six Sigma Makes Its Way to the Contact Center
  • Six Sigma And Web Marketing
  • How Six Sigma Can Help ITIL Service Level Management
  • Lean Six Sigma Meets Darwin And Market Segmentation
  • Metrics, Six Sigma, And Improved ROI
  • What CIOs And CTOs Need To Know About Lean Six Sigma
  • Concepts for Green Belt Coaching
  • Thinking Statistically With Six Sigma
  • Reducing Cycle Time For Six Sigma Projects
  • Six Sigma And The Public School System
  • The Boon and the Bane in Outsourcing
  • Outsourcing and Effective SEO
  • What Makes a Good Outsourcing Contract
  • How Outsourcing Works and Its Benefits
  • Workforce Management in Call Centers
  •  
     
         
         
        © 2012 interpret.zar.vg